We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.
Other improvements include updated:
- Street lighting
- Traffic signs
- Striping
- Storm drainage
- Water quality facilities
Design start: October 2022
Design finish (expected): June 2024
ROW acquisition (expected): May 2024-February 2025
Construction start (expected): March 2025
Construction finish (expected): August 2026
Sign up to receive project updates by email
Update
4/16/2024: We are presenting our cyclist and pedestrian improvement options to at a Board of County Commissioners Work Session. We hope to receive feedback about how to proceed with design.
Funding
Cost Estimate: $6.3 million
Funding sources:
- MSTIP Bonding Cost-sharing Program
- Bonny Slope West System Development Charge