Safety Projects - 2015 Minor Betterment & URMD

Current Activity - completed

Verboort Road Activity Update 9/22/2016: Construction began on this Minor Betterment project between Heesacker Rd and Visitation Rd with placing storm pipe and storm inlets and filling in the roadside ditch. The contractor is scheduled to pour the concrete sidewalk during the last week of September.

Activity Update 01/19/2016:

Substantially complete
119th Avenue @ Lovejoy Street
209th Avenue
Barnes Road
Cornell Road
Kinnaman Road
Rock Road
Thompson Road
Walker Road

Remaining projects
Verboort Road - Construction is scheduled to occur summer 2016.