80th Avenue Culvert Replacement

Current Activity - construction


Activity Update 8/31/17: SW 80th Avenue is now open. Final work will continue with periodic lane closures, 9 a.m.-3:30 p.m. weekdays.


Past Updates
_______________________


Activity Update 8/21/17: SW 80th Avenue, between Elmwood and Hemlock streets, will remain closed through Sept. 1. The road closure for culvert replacement has been extended due to unforeseen site conditions.


Activity Update 7/5/17: 80th Avenue culvert replacement and road closure are scheduled for Aug. 2-23. Click on detour map to enlarge:

80th Avenue detour map



Activity Update 11/17/16: This project is currently in the design phase. Construction is anticipated to occur during Summer 2017. SW 80th Ave is expected to be closed for about three weeks while the new culvert is installed.