Completed Transportation Projects

Project
sort:
From/To Activity
sort:
Estimated Completion
sort:
**Archived Projects - Completed 3+ Years Ago / Completed 01/31/2009
Brookwood/Alexander Roundabout Alexander Street/Brookwood Avenue Completed 05/29/2009
10th Avenue (Hillsboro) Main St/Baseline Rd Completed 06/26/2009
209th Avenue Bridge Stoddard Dr/Parker Ct Completed 10/30/2009
Murray/Cornell Corridor Improvements Hwy 26/Science Park Dr Completed 12/18/2009
170th/173rd Avenue Walker Rd/Baseline Rd Completed 12/31/2009
River Road  Rood Bridge Rd/Davis Rd Completed 06/30/2010
Cornelius Schefflin Road - Segment E North of Council Creek Bridge/Verboort Roundabout Completed 06/30/2010
Council Creek Bridge Cornelius-Schefflin Rd/ Completed 06/30/2010
Spiesschaert Road /Council Creek Completed 06/30/2010
Kaiser Road Intersections Laidlaw Rd/Bethany Blvd Completed 09/30/2010
Susbauer Railroad Crossing / Completed 10/01/2010
Sellers Road Realignment Sellers Rd/Banks Rd Completed 10/15/2010
Banks/Vernonia Trail Extension Banks Rd/Sellers Rd Completed 10/15/2010
185th Avenue Shaw St/Kinnaman Rd Completed 12/17/2010
Tualatin-Sherwood/Gerda Signal Gerda Ln/Tualatin-Sherwood Rd Completed 12/29/2010
Saltzman Road Bauer Woods Dr/Cornell Rd Completed 12/31/2010
Tualatin-Sherwood Road (ITS - Phase 1) I-5/Teton Ave Completed 05/31/2011
Glencoe Road Hwy 26/West Union Rd Completed 06/30/2011
Cornelius Pass Road  Frances St/Wilkins St Completed 07/15/2011
99W at Hall and Greenburg/Main Hall Blvd/Greenburg Rd/Main St Completed 08/31/2011
David Hill Road Extension (Phase 1) Brooke St/700 feet east Completed 02/03/2012
185th Avenue Westview High School/West Union Rd Completed 06/29/2012
Scholls Ferry/River Road Intersection River Rd/Scholls Ferry Rd Completed 06/29/2012
Glencoe Road Bridge /McKay Creek Completed 09/30/2012
Highway 26 Cornell Rd/185th Ave Completed 09/30/2012
Old Cornelius Pass Road Bridge /Rock Creek Completed 10/22/2012
Bull Mountain/Roshak Intersection Roshak Rd/Bull Mountain Rd Completed 11/16/2012
119th Avenue McDaniel Rd/Cornell Rd Completed 11/23/2012
Meacham Road Bridge /East Fork Dairy Creek Completed 11/30/2012
Rock Creek Trail Crossing /Evergreen Road Completed 11/30/2012
Brookwood Avenue TV Hwy/Baseline Rd/Main St Completed 12/31/2012
Cornelius Pass Road Aloclek Dr/Wilkins St Completed 04/19/2013
Johnson School Road Bridge /Davis Creek Completed 04/26/2013
Evergreen Road 253rd Ave/25th Ave Completed 05/10/2013
Scholls Ferry Road Bridge /Fanno Creek Completed 05/15/2013
Leahy Road and Stark Street 89th Av-88th Av/90th Av-88th Av Completed 08/31/2013
Old Highway 47 Bridge /Scoggins Creek Completed 11/29/2013
Boones Ferry Road Day Rd/Norwood Rd Completed 06/30/2014
Bethany Boulevard Cornell Rd/West Union Rd Completed 06/30/2014
P15 (North Bethany area) Brugger Rd/Springville Rd Construction 07/18/2014