Farmington Road (Murray to Hocken)

Current Activity - construction


Activity Update 6/1/2016: Construction work is ongoing. Expect excavation of Farmington Road (June 1 - June 14) and Murray Blvd (June 10 - 17), as well as prepping and pouring walkways beginning June 1 - 10. 

PGE begins to install utility poles June 6 west of Murray Blvd and will close the right-hand westbound lane between 9:00 a.m. - 3:30 p.m. Expect the same activity on the east side of the road beginning June 13, then switching to the west side once its complete. The right-hand lane may again be restricted from 9:00 a.m. - 3:30 p.m. Flaggers will be onsite to help direct traffic. Expect daytime delays. 

Left turns remain prohibited throughout the corridor along Farmington - plan accordingly. Travelers should expect long delays or are encouraged to use alternate routes (TV Highway or Allen Boulevard).



Photo: Groundbreaking ceremony held on June 1, 2015

Farmington Groundbreaking June 1, 2015



Project Simulation Video

View our design consultant's (HHPR) video that does a simulation flyover of the improvements planned for Farmington Road.