Kaiser Road (Two Ponds to Vance) Gain Share

Current Activity - construction


Activity update Aug. 17, 2017: 100226 pavingPaving is underway on Kaiser Road bike lanes. Project is expected to be substantially complete by Aug. 25.

 




Past Updates
_______________________

Activity update March 28, 2017: Design strip map is now available. Strip Map


Activity update Jan. 24, 2017: Construction is scheduled to begin in spring 2017.