Oleson Road Bridge over Fanno Creek

Current Activity - design


Activity Update 2/26/14: This project is in the final stages of design and all necessary easements have been acquired.

Prior to mid-March, a building demolition contract will start work to tear down and remove the apartment building at the southwest corner of the bridge. Expect periodic delays associated with equipment access to the site for this work.

During the months of March through May, utilities crews will be working in and adjacent to the roadway to relocate utility lines in preparation for the bridge construction work. Expect intermittent lane closures associated with this work. 

This project is scheduled to go to bid in April 2014 with bridge and road construction anticipated to begin June 2014.

An eight month road closure is necessary to replace the bridge. Click on the "Closures" link to the right for road closure information.

January 2014 Project Update Newsletter (mailed 1/7/14)