Oleson Road Bridge over Fanno Creek

Project Timeline

Estimated completion date: 05/31/2015


Timeline summary – This updated timeline chart provides an estimated activity schedule for this bridge replacement project and the Oleson Road realignment project.  (Funding has not been identified for the realignment project at this time.)

Bridge replacement project timeline details:

  • Demo and removal of the 8-unit apartment complex - 2/28/14 until completed
  • Utility contractor work relocating lines - March-May 2014
  • Project bid and road/bridge contractor selection – April/May 2014
  • “Meet the Contractor” open house – May/June 2014
  • Road closure – July 2014 through Feb/March 2015
  • Road and bridge construction – June 2014 through May 2015

Note: Dates are subject to change due to weather and/or other unforeseeable events.