Road Widening and Paving 2015-16

Current Activity - completed

Update: 9/23/16

Due to delays in utility relocations, and conflicts with our contractor's schedule, the 185th Avenue from Bany to Farmington project is rescheduled for next spring (2017).

Update: 7/20/16

Relocation of utilities on 185th Avenue from Bany to Farmington has taken longer than anticipated. The contractor will return to complete the widening and paving of this section in September.

Update: 6/6/16

Paving on River and Rosedale roads is complete. Striping and pavement markers will be replaced June 13 through June 15.

Widening and paving of 185th Avenue from Bany to Farmington has been delayed pending relocation of utilities. The expected completion of this work has been extended to July 31.

Update: 5/20/16

Paving has been delayed due to recent rain. River Road paving is now scheduled for May 23 through May 27. Rosedale Road paving will be May 31 and June 1.

Update: 5/5/16

Paving River Road has been delayed to May 16 through May 23. Rosedale Road paving is now scheduled for May 24 and 25.

Update: 5/2/16

River Road from Farmington to Oakhurst will be paved starting Wednesday, May 4, through May 11. Hours of work are 8:30 a.m. to 4 p.m. The road will remain open with flaggers controlling one-way traffic. Expect delays or use an alternate route. Road striping is scheduled for May 23 and 24.

Rosedale Road from River to 229th is scheduled for paving May 12 and 13, with striping on May 23 and 24.

Update: 4/19/16

Paving on Golf Course Road starts Monday, April 25, and will continue through April 29. Driveway and shoulder work continues through May 6, with road striping scheduled for May 17 and 18. This schedule may change as the work is dependent on weather.

Update: 10/30/15

Road widening work on River Road and shoulder rocking on both Golf Course and River will be completed today. Temporary paint striping on both roads is planned for next week when dry weather is expected.

Update: 10/16/15

Road widening work on Golf Course Road is completed. Shoulder rocking should be complete by October 30.

Road widening work continues on River Road. Expect delays between 8:30 a.m. and 4 p.m. Monday through Friday, with extended work hours on Saturdays. Work should be complete by October 30.

Update: 10/2/15

Road widening work continues on Golf Course Road. Shoulder paving should be complete by October 2. Shoulder rock should be complete by October 23.

Road widening work is in progress on River Road. Widening should be complete by October 23. Expect delays between 8:30 a.m. and 4 p.m. Monday through Friday, with extended work hours on Saturdays.

Update: 9/11/15

Road widening work is in progress on Golf Course Road. Work on this road should be completed by September 25.

Update: 7/10/15

Adjacent residents are being notified of need to remove landscaping and other installations from the public right-of-way that interfere with the project.

Bids were opened on July 8, 2015. The apparent low bidder is Eagle Elsner Inc. Work is expected to begin mid-August 2015 and be complete by June 30, 2016.