Scholls Ferry Road (Roy Rogers to Teal)

About

The existing section of SW Scholls Ferry Road between Roy Rogers Road and Teal Boulevard is a two-lane roadway providing access between SW Murray Boulevard and the growing residential areas in southwest Beaverton. Currently turning onto or from SW Scholls Ferry Road can be challenging due to heavy traffic volumes. This section of roadway also lacks bicycle facilities and has intermittent sections of sidewalk.

The proposed project will widen SW Scholls Ferry Road to five lanes, which will consist of two travel lanes in each direction with a continuous center turn lane. This will reduce traffic congestion from the intersection of Teal Boulevard west through Roy Rogers Road. Additional improvements include sidewalks, bicycle lanes, street lighting and improved sight distance at the intersections.

Media Releases:
Final Milling and Paving - September 2 - 13

Project Contact

Kim Haughn
Public Information Officer
(503) 846-7822
Email: Kim Haughn

Project Map

100099 Scholls-RRR to Teal Vic Map

Meetings


Open House #1 - 10/03/12

Displays:

Funding Information

MSTIP
$12 Million


MSTIP
- Major Streets Transportation Improvement Program

The total project cost noted above includes the estimated cost of design, right-of-way and construction and is subject to change.

Current Activity - construction


Activity Update 9/19/14
: Final paving is complete. Striping will occur in the next week or two, depending on the weather. Remaining work includes installing street lights, wrapping up minor punch-list items and site clean up.


Thanks for your continued patience during this project!



Please note: The speed limit has been temporarily reduced to 30 mph for the safety of the workers and the drivers. Keep in mind that traffic fines are often doubled when violations occur in a work zone. This reduced speed is effective 24 hours a day whether workers are present or not. 

Scholls Ferry Road construction Aug 2014

Design


Design strip map - Draft (subject to change)

Traffic Analysis and Design Report - Final

Noise Impact Analysis Report

Project Timeline

Construction start date: 08/15/2013
Estimated completion date: 12/31/2014


Note: Dates are subject to change due to weather and/or other unforeseeable events.