Scholls Ferry Road (Roy Rogers to Teal)

About

The section of Scholls Ferry Road between Roy Rogers Road and Teal Boulevard was previously a two-lane roadway providing access between Murray Boulevard and the growing residential areas in southwest Beaverton. Turning onto or from SW Scholls Ferry Road was challenging due to heavy traffic volumes. This section of roadway also lacked bicycle facilities and had intermittent sections of sidewalk.

This project widened Scholls Ferry Road to five lanes - two travel lanes in each direction with a continuous center turn lane. This will reduce traffic congestion from the intersection of Teal Boulevard west through Roy Rogers Road. Additional improvements included sidewalks, bicycle lanes, street lighting and improved sight distance at the intersections.

In conjunction with this project, City of Tigard, City of Beaverton and Clean Water Services also upgraded their utility lines. By coordinating all four projects during approximately the same time frame, it resulted in an overall cost savings and limited the duration of traffic impacts by tacking on to the road widening project's timeline.

Media Releases:
Final Milling and Paving - September 2 - 13, 2014

Project Contact

Kim Haughn
Public Information Officer
(503) 846-7822
Email: Kim Haughn

Project Map

100099 Scholls-RRR to Teal Vic Map

Meetings


Open House #1 - 10/03/12

Displays:

Funding Information

MSTIP
$12 Million


MSTIP
- Major Streets Transportation Improvement Program

The total project cost noted above includes the estimated cost of design, right-of-way and construction and is subject to change.

Current Activity - completed


Activity Update 5/19/14
: This project is substantially complete. Remaining work includes the planting of several hundred trees along the corridor this fall. The trees will then be maintained by the City of Beaverton.


Many thanks for everyone's patience during this project and we hope you enjoy the improvements!


Design


Design strip map - Draft (subject to change)

Traffic Analysis and Design Report - Final

Noise Impact Analysis Report

Project Timeline

Construction start date: 08/15/2013
Estimated completion date: 12/31/2014


Note: Dates are subject to change due to weather and/or other unforeseeable events.