Scholls Ferry Road Bridge over Fanno Creek
This project replaced the substandard Scholls Ferry Road bridge over Fanno Creek, located between Denney Road and Allen Boulevard. The new bridge structure is longer, wider and built above the flood plain. It includes two travel lanes, a center turn lane, bike lanes and sidewalks.
Media releases:
Paving Scheduled for April 9 through 12, 2013
Paving Scheduled for February 15 & 18, 2013
Periodic road closures for beam delivery December 19 & 20, 2012
Open House - September 21, 2011
Open House - May 9, 2012
Project Contact
![]()
Matt Meier
Project Manager
(503) 846-7829
Email: Matt Meier
Project Map
![]()
Meetings
![]()
Open House #1 - 9/21/11
Open House Summary
Comments Summary
Meet the Contractor Open House - 5/9/12
Open House Summary
Comments Summary
Funding Information
![]()
MSTIP
$5.9 Million
MSTIP - Major Streets and Transportation Improvement Program (Phase 3c)
The total project cost above includes the estimated cost of design, right-of-way and construction and is subject to change.
Current Activity - completed
![]()
This project is substantially complete! Crews will wrap up minor punch-list items in the area through the end of May.
Thank you, everyone, for your patience during construction while our contractor replaced the bridge. We hope you enjoy the new bridge!
Previous Newsletters:
Construction Update - February 2013
Construction Update - December 2012
Construction Update - August 2012
Construction Update - June 2012
Project Timeline
![]()
Construction start date: 05/14/2012
Estimated completion date: 05/15/2013
Note: Dates are subject to change due to weather and/or other unforeseeable events.