Tualatin-Sherwood Road RR Crossing

Project Timeline

Construction start date: 08/21/2015
Estimated completion date: 08/25/2015

 

Preparatory work and utility coordination: spring and early summer 2015

Project staging: August 1-20, 2015

Road closure starts: August 21, 2015 (after evening commute)

Road reopens: August 24, 2015

Work area cleanup: August 24-25, 2015 (minimal traffic impact)

Note: Dates are subject to change due to weather and/or unforeseeable events.