Walker Road (173rd to Murray)

About

Walker Road between 173rd Avenue and Murray Boulevard is a heavily used east-west arterial roadway with varying three to five lane sections and intermittent bicycle and pedestrian facilities.  

This project will improve this section of Walker Road to five lanes (two travel lanes in each direction with a center turn lane) with continuous bicycle and pedestrian facilities. Storm drainage will be upgraded and additional street lighting will be installed.

For the most recent status on this project, click on the 'Activity' link to the right.

Media Releases:
Open House - January 23, 2014
Open House - April 24, 2013

Project Contact

Matt Costigan
Project Manager
(503) 846-7825
Email: Matt Costigan

Project Map

Walker Rd Vicinity Map

Meetings


Open House #1 - April 24, 2013


Open House #2 - January 23, 2014

Funding Information

MSTIP
$15.7 Million


This project is funded through phase 3D of the Major Streets Transportation Improvement Program (MSTIP).

Please note: The total project cost noted above includes the estimated cost of design, right-of-way and construction and is subject to change.


 

Current Activity - design


Activity Update 5/5/14: This project is being postponed for approximately two years. View the postcard mailer that was sent out to area residents this week for complete details. 

The following is an updated map showing the tentative schedule for projects in the area, including the delayed Walker Road project:
Walker Road block projects map



Project Update Newsletter - May 2014

Project Timeline

Estimated completion date: 12/31/2019

 
This project is being postponed until 2018/2019.

Note: Dates are subject to change due to weather and/or other unforeseeable events.