Walker Road (173rd to Schendel)

About

Walker Road is a heavily used east-west arterial roadway with varying travel lane sections (any where from two to five lanes) and intermittent bicycle and pedestrian facilities.  

Phase 1 of the Walker Road project will improve the roadway from 173rd Avenue to Schendel Avenue to five lanes (two travel lanes in each direction with a center turn lane) and will include continuous bicycle and pedestrian facilities. Storm drainage will be upgraded and additional street lighting will be installed.

This $5.5 million project is funded through phases 3c and 3d of the County's Major Streets Transportation Improvement Program (MSTIP). The total project cost includes the estimated cost of design, right-of-way and construction and is subject to change.

CPO 7; Commissioner District 2

Sign-up for Walker Road project e-newsletter updates!

Media Releases
Open House - May 19, 2015
Open House - January 23, 2014

Open House - April 24, 2013


Project Contact

Matt Costigan
Project Manager
503-846-7825
Email: Matt Costigan

Additional Resources

Current Activity - construction


Activity Update 6/30/16: Daytimetraffic will be directed by flaggers from 7:30 a.m. to 3 p.m. on Tuesday, July 5 to permit a contractor to perform construction activities related to the project. Choose an alternate route or be prepared for long delays.

Activity Update 5/25/16:

Construction activity of the first phase will begin early June 2016. Initial activity includes installation of construction signage, sediment fencing and erosion control devices, and the removal of vegetation in the project area.



The Walker Road project has been split into two phases.
  • Phase 1: 173rd to Schendel is scheduled for construction to begin June 2016 with completion by December 2016. 
  • Phase 2: Schendel to Murray is scheduled for construction to begin in 2018 with completion in 2019. 


The following is a map showing the tentative schedule for all projects in the area, including phase 2 of the Walker Road project (Schendel to Murray). Dates and project limits are subject to change.

Walker area projects vicinity map (as of May 2015)



Project e-Newsletters

May 2016

May 2015
May 2014

Design

 

Meet the Contractor Open House #4 - May 24, 2016

 

Open House #3 - May 19, 2015



Open House #2 - January 23, 2014



Open House # 1 - April 24, 2013

 

Project Timeline

Estimated completion date: 11/30/2016


Construction is scheduled to begin spring 2016.

NOTE: Dates are subject to change due to weather and/or other unforeseeable events.


Additional Resources