Walker Road (173rd to Schendel) - Phase 1

About

Walker Road is a heavily used east-west arterial roadway with varying travel lane sections (any where from two to five lanes) and intermittent bicycle and pedestrian facilities.  

Phase 1 of the Walker Road project will improve the roadway from 173rd Avenue to Schendel Avenue to five lanes (two travel lanes in each direction with a center turn lane) and will include continuous bicycle and pedestrian facilities. Storm drainage will be upgraded and additional street lighting will be installed.

For the most recent status on this project, click on the 'Activity' link to the right.

Media Releases:
Open House - May 19, 2015
Open House - January 23, 2014

Open House - April 24, 2013

Project Contact

Matt Costigan
Project Manager
503-846-7825
Email: Matt Costigan

Additional Resources

Meetings


Open House #3 - May 19, 2015



Open House #2 - January 23, 2014

Funding Information

MSTIP
$5.5 Million


This project is funded through phases 3c and 3d of the County's Major Streets Transportation Improvement Program (MSTIP).

NOTE: The total project cost noted above includes the estimated cost of design, right-of-way and construction and is subject to change.


 

Current Activity - design


Activity Update 5/21/15:

A project open house was held on Tuesday, May 19, 2015 at Kaleo Covenant Church. Over 40 people stopped by to learn more about Phase 1 of the Walker Road project and the upcoming 158th Avenue project.

To view the displays from the open house, click on the "Events" link to the right.



The Walker Road project has been split into two phases.


  • Phase 1: 173rd to Schendel is scheduled for construction to begin spring 2016 with completion by November 2016. 
  • Phase 2: Schendel to Murray is scheduled for construction to begin in 2018 with completion in 2019. 

The following is a map showing the tentative schedule for all projects in the area, including phase 2 of the Walker Road project (Schendel to Murray). Dates and project limits are subject to change.

Walker area projects vicinity map (as of May 2015)


Project Update Newsletter - May 2015
Project Update Newsletter - May 2014

Project Timeline

Estimated completion date: 11/30/2016


Construction is scheduled to begin spring 2016.

NOTE: Dates are subject to change due to weather and/or other unforeseeable events.