Walker Road (173rd to Schendel) - Phase 1

Current Activity - construction


Activity Update 5/25/16:

Construction activity of the first phase will begin early June 2016. Initial activity includes installation of construction signage, sediment fencing and erosion control devices, and the removal of vegetation in the project area.



The Walker Road project has been split into two phases.
  • Phase 1: 173rd to Schendel is scheduled for construction to begin June 2016 with completion by December 2016. 
  • Phase 2: Schendel to Murray is scheduled for construction to begin in 2018 with completion in 2019. 


The following is a map showing the tentative schedule for all projects in the area, including phase 2 of the Walker Road project (Schendel to Murray). Dates and project limits are subject to change.

Walker area projects vicinity map (as of May 2015)