Walnut St (116th to Tiedeman)

Project Timeline

Construction start date: 03/14/2016
Estimated completion date: 05/01/2017

 
Vegetation removal - Jan 2016 - Feb 2016
Road construction - Mar 2016 - May 2017
3-week road closure - July 25 - August 15, 2016

Construction Bid/Award
Fall 2015 - The construction contract was publicized for bid offers. On December 2 construction contract bids were open. Rotschy, Inc. was awarded the contract on December 15 and a contract was executed on January 25, 2016. Road construction activity began March 8, 2016.

Note: Dates are subject to change due to weather and/or other unforeseeable events.