175th Avenue/Kemmer Road Intersection

Current Activity - construction

 

Visit GetUsThere.org for Roy Rogers Road area traffic alerts.

Visit wc-roads.com for Washington County traffic alerts.
 

Activity Update 11/16/2018: The 175th Avenue and Kemmer Road roundabout opened late Nov. 15. Work remaining includes connection of street lights to a permanent electrical source by PGE and landscaping. Permanent striping and safety markings will be installed in spring 2019.


Prior Updates
_________________________

Activity Update: 10/26/2018: The 175th Avenue/Kemmer Road intersection closure has been delayed to Nov. 1-16. The Kemmer Road closure, between 175th and 176th avenues, will be extended through Nov. 16. Media release Detour


Activity Update 10/22/2018: From Oct. 29-Nov. 13, 175th Avenue will be closed at Kemmer Road for construction of a roundabout. Media release

Activity Update 10/12/2018: Kemmer Road will remain closed west of 175th Avenue through Nov. 12. In addition, 175th Avenue will be closed at Kemmer Road Oct. 29-Nov. 12. Media release Detour

175th Avenue detour map


Activity Update 9/5/2018: Kemmer Road, between 175th and 176th avenues, will be closed Sept. 17-Oct. 16. Media release Detour


Kemmer Road detour map

 

 

Activity Update 4/10/2018: Construction is set to begin April 16 with lane closures 9 a.m.-3:30 p.m. weekdays April 16 through August 31. Two closures will be scheduled later in construction. Media release

Activity Update 2/22/2018: Construction contract for the 175th Avenue/Kemmer Road project has been awarded to Kerr Contractors by the Board of County Commissioners at their Feb. 20, 2018 meeting.

Activity Update 4/20/2017: Open house displays are now available on the Design tab.

Activity Update 3/21/2017: Open house scheduled for April 19. Media release

Activity Update 7/5/2016: Staff completed the alternatives analysis, which includes feedback from the April open house. The roundabout alternative was selected and will be advanced to the next stage of design. A second open house will be scheduled when the design plans are 75% complete.

 

Displays from the April 2016 open house area posted to the 'Design' tab.

This project is currently in the preliminary design phase. Construction is anticipated to occur in 2018.