192nd Avenue (FY 2020-22 Pedestrian Improvement)
Project Timeline
Construction start date: 03/01/2022Estimated completion date: 07/29/2022
Note: Project dates are estimates and subject to change
- Project design: July 2020-July 2021
- Right-of-way acquisition discussions: November 2021-March 2022
- Contractor bid process: January-February 2022
- Start of construction: March 2022
- Project completion: July 2022