69th Avenue Bridge at Rock Creek

Current Activity - completed

 

Project Update 6/19/2020: 69th Avenue has been paved and striped. The road is expected to reopen on June 26, after guard rails and pedestrian safety rails have been completed.

69th Avenue bridge recently paved

 

Past Updates
_________________________

Project Update 4/1/2020: The 69th Avenue closure will be extended through June 25 due to construction delays. The project schedule is an estimate and subject to change due to weather or unforeseen circumstances. Detour

 

Project Update 2/28/2020: Girders have been set for the new 69th Avenue bridge. 

Girders set on 69th Avenue bridge

Project Update 11/4/2019: Bridge construction is progressing. Neighbors may be impacted by daytime noise.

 

Project Update 7/31/2019: An open house for the 69th Avenue Bridge Replacement Project is 5-7 p.m. Aug. 14 at the Unitarian Universalist Community Church, 6815 NE Birch St. A closure of 69th Avenue, at Rock Creek. will begin Aug. 15. The road is expected to reopen in May. See map

 

Project Update 2/22/2019: Project is tentatively expected to begin construction in June 2019 with completion expected in the summer of 2020. Project dates are estimates and subject to change.

 

Project update 9/22/2017: Project open house scheduled for 5-7 p.m. Sept. 22 at Orenco Elementary School, 7030 NW Birch St. Media release

 

Project Update 3/14/2017: Design survey and geotechnical drilling will begin April 3.