Cedar Hills Boulevard/U.S. 26 Intersection

Current Activity - construction


Visit wc-roads.com for Washington County traffic alerts.
 

Activity Update 4/26/2019: In celebration of the new signal at the eastbound U.S. 26 off-ramp at Cedar Hills Boulevard, travelers can pick up free coffee from 7-9 a.m. Thursday, May 9, in the Peterkort Towne Square at Cedar Hills Boulevard and Barnes Road. Media release

 

Prior Updates
________________________

 

Activity Update 2/7/2019: Base paving of the widened ramp was completed in January. Sidewalks are expected to be completed by Feb. 28, depending on the weather.
 

 

Activity Update 11/21/2018: Construction begins Nov. 26 with lane closures on Cedar Hills Boulevard under the U.S. 26 overpass intermittently, 9 a.m.-3 p.m. weekdays and 7 a.m.-7 p.m. weekends through April 30, 2019.

 

Project Update 6/6/2018: Open house exhibits are now available in the Design section of this page.

 

Project Update 5/15/2018: A project involvement event has been scheduled from 5-7 p.m. June 6 at Cedar Park Middle School, 11100 SW Park Way. Media release