Division Street Culvert Replacement

 

About this project

Division Street logo

DivisionStCulverts

Enlarge

There are two undersized culverts on Division Street between 149th Avenue and 150th Court that have caused flooding in the past. We will replace them with a single larger culvert. This will improve water flow and improve fish passage upstream.

Update 7/14/2022: This project has been delayed indefinitely
Contact: Operations and Maintenance,
Land Use & Transportation, 503-846-7623

 

Funding
 

  • Cost is estimated at $530,000.

  • Funding Sources:

    • Road Fund