Dixie Mountain Road Culvert Replacement

 

About this project

Wordmark_Dixie Mountain Road

DixieMntCulvert51849

Enlarge

We installed two temporary culverts as emergency repairs on Dixie Mountain Road. We will replace the temporary culverts with a single metal pipe. At the same time, we will rebuild the road base to fill any voids that resulted from the previous culvert failure and were not addressed during the emergency repairs. The culverts are located near milepost 0.4.

Dixie Mountain Road will remain open with lane closures during construction.

Construction start (expected): August 29, 2022

Construction finish (expected): September 29, 2022
 

Update 9/8/2022: Construction is underway.

Contact: Operations and Maintenance,
Land Use & Transportation, 503-846-7623

 

Funding
 

  • Cost is estimated at $362,000.

  • Funding Sources:

    • Road Fund