Elwert Road/Kruger Road Intersection

Current Activity - construction

 

Activity Update 4/9/2020: Access between Elwert/Kruger roads and Highway 99W will close April 13-June 30 for construction of a roundabout and other work. Elwert and Kruger roads will remain open to traffic with lane closures. Flaggers may stop traffic for up to 10 minutes at a time. Travelers must use Edy Road to access Highway 99W and SW Sunset Boulevard. Detour Media release

Elwert and Kruger roads detour map phase 3

 

 

Past Updates
_______________________

Activity Update 1/16/2020: Kruger Road will remain closed until Feb. 3. Elwert Road, between Kruger and Edy roads, and Haide Road, between Elwert Road and the future Sherwood High School access road, will close Feb. 3-April 1. Local access will be maintained to driveways. All other traffic must use the detour. Media release

 

Activity Update 11/21/2019: Kruger Road is expected to close Dec. 4-Jan. 31. Access will be maintained to local driveways; all through traffic must use the detourMedia release

 

Activity Update 10/29/2019: Due to unforeseen circumstances, the Elwert Road closure has been delayed. Information will be made available as soon as the closure is rescheduled.

 

Activity Update 10/23/2019: Elwert Road, between Pacific Highway 99W and Kruger Road, is expected to close Oct. 30-Jan. 15 for construction. Traffic must use Edy Road for access to/from Highway 99W. Detour

 

Activity Update 6/24/2019: Construction is expected to begin in early August.

 

Activity Update 3/8/2019: Selected trees have been removed from the project area in anticipation of construction, expected to begin in July.

 

Activity Update 6/5/2018: Open house exhibits are now available on the Design section of this page.

 

Activity Update 2/2/2018: Project design is being revised in coordination with the Sherwood School District to incorporate road improvements associated with the construction of a new high school. New anticipated completion date is summer 2020.

 


Activity Update 4/19/2016: A project open house will be held on May 12 at Middleton Elementary School from 5 to 7 p.m. The public is invited to stop by anytime during open house hours to learn more about the proposed design and to provide comments to the project team. No formal presentation is planned.

This project is approved for up to 30% design.

Remaining design, needed right-of-way acquisition and construction will be authorized at a future date in coordination with the City of Sherwood. Construction is anticipated to begin in 2018 or 2019 - subject to change.