Farmington Road and River Road intersection

 

About this project

Farmington Road and River Road intersection logo

Farmington Road and River Road intersection map

Enlarge

The Farmington and River roads intersection sees a lot of traffic. During commute times, travelers have long wait times to get through the intersection. The all-way stop is limiting traffic in all directions.

We plan to build a roundabout that will limit impacts to property owners, the floodplain and the environment.  

Construction start (expected): Summer 2022
Construction finish (expected): December 2022
 


Update 7/16/2021:  The right-of-way acquisition process is underway.

Sign up to receive the project enewsletter.

Contact: Capital Project Services, Land Use & Transportation, 503-846-7800
 


Funding
 


Newsletters
 


Prior events and comment opportunities


Online Open House - April 17-May 3, 2020