Gaston Road Bridge Replacement

Current Activity - construction

 

Activity Update 8/24/2020: The Gaston Road closure will now begin Aug. 26 due to unforeseen delays.

 

Past Updates

Activity Update 8/7/2020: Gaston Road is closing Aug. 24-Nov. 30 for bridge replacement. Media release Detour

 

Activity Update 6/30/2020: The project is out for bid; construction is expected to start in mid-August.

 

Activity Update 10/18/2019: The open house exhibits are available on the design page.

 

Activity Update 6/13/2019: Gaston Road will close June 25-26, at the bridge over Wapato Creek, between Highway 47 and Spring Hill Road, for geotechnical drilling. Detour