Safety improvements are needed on Martin Road due to an increase in freight and commercial traffic. The road provides a connection between U.S. 26 and the city of Forest Grove.
We have installed a roundabout at Highway 47 and Martin Road. We are widening the road shoulders on Martin Road to the roundabout. We will also replace three culverts on Martin Road at Council Creek with a single-span concrete bridge.
Construction start: July 2023
Construction finish (expected): April 2024
Sign up to receive project updates by email
Update
4/25/2024: Join us from 9-10 a.m. on Saturday, May 11 to celebrate the completion of the Martin Road roundabout and shoulder widening.
Celebration will take place at Martin Road and old Martin Road (see map).
Funding
Cost: $10.2 million (estimate)
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP 3e)
- City of Forest Grove
Prior events and comment opportunities
Meet the contractor open house: May 17, 2023
Open house: March 26-April 11, 2021