Pongratz Road culvert replacement project

 

About this project

Pongrats Road culvert logo

Pongratz Road culvert replacement location

Enlarge

The culvert on Pongratz Road, between Tolke Road and Ardabeth Lane, is too small and often clogs. We are replacing the culvert with a larger metal pipe to improve water flow and allow fish to pass upstream.

We are replacing the culvert at the same time as the bridge over Whitcher Creek, east of Tolke Road. More information about the bridge replacement is available on the project page

The project is starting in summer 2021 (tentative) and ending in October. Pongratz Road will close during construction. 

Construction start (expected): August 2021
Construction finish (expected): 9/30/2021

 


Update 7/28/2021: Pongratz Road will close Aug. 2-30 for culvert replacement. The Pongratz Road bridge replacement project will follow.

Detour map

Contact: Operations and Maintenance,
Land Use & Transportation, 503-846-7623

 

Funding
 

  • $450,000 (2020 estimate)

  • Funding sources:

    • Road Fund

 

Prior events and comment opportunities


Open house April 2-18, 2021: