Road maintenance activities FY 2021-22

 

Ops Road Maintenance logo

Paving Logo 2021

Travelers should also monitor wc-roads.com and/or Twitter for alerts to avoid road work and delays.

Completed projects are listed below as well. If you have concerns about the condition of your road, please report them via our Service Request online form.

 

Paving
The dates below are for grinding and paving activites, which involve weekday lane closures unless otherwise noted. Dates and times are may change due to weather and contractor availability. Sign up here to be notified of changes to the paving schedule.  (Updated 9/20/21)

  • 143rd Avenue, between Cornell and Thompson roads (Road Fund): Aug. 23-Sept. 9. Nighttime paving Sept. 20-22
  • Beef Bend Road, between Highway 99 and Roy Rogers Road (Road Fund): July 12-Aug. 12 & Sept. 8-13 (weekdays only)
  • Davis Road, between 160th and 165th avenues (Road Fund): Sept. 29-30
  • Science Park Drive, between Murray Boulevard and Cornell Road (Road Fund): Sept. 14-30

 

Surface stabilization
UPDATE as of Aug. 23: Earlier this summer, we were unable to get the product we use for Surface Stabilization, due to mechanical failures at the factory where it is made. Surface Stabilization is most effective between June and September. Even though some product is now available, we've made the decision to cancel our Surface Stabilization program for this season. We are hopeful that our Surface Stabilization program will resume for the summer 2022 season.

 


Completed projects

Monument box installation

  • 185th Avenue, at the intersection of Madeline Street: complete
  • Brookman Road, between Middleton Road and the railroad crossing: complete
  • Dairy Creek Road, between Murphy Road and Cedar Lane: complete
  • Dober Road, between Riedwig and Iowa Hill roads: complete
  • Ecole Avenue, between Jenkins and Walker roads: complete
  • Fern Hill Road, between Highway 47 and Springhill Road: complete
  • Hahn Road, between Davidson Road and end-of-pavement: complete
  • Iowa Hill Road, between Dober and Gnos roads: complete
  • Madeline Street, between 185th and 192nd avenues: complete
  • Mountaindale Road, between Dairy Creek Road and 448 feet west of Dairy Creek Road: complete
  • Mountaindale Road, at the intersection with Hahn Road: complete
  • Mount Richmond Road, between South Road and the Yamhill County line: complete
  • Old Cornelius Pass Road, between Cornelius Pass and Phillips roads: complete
  • Patton Valley Road, between Old Highway 47 and Richmond Road: complete
  • Rosa Road, between 196th and 198th avenues: complete
  • Scholls Ferry Road, between Scholls-Sherwood Road and bridge #202995: complete
  • Scholls-Sherwood Road, between Scholls Ferry Road and 200 feet south of Munger Lane: complete
  • Springhill Road, between Withycombe and Vandehey roads: complete
  • Stringtown Road, between Ihrig and Gales Creek roads: complete
  • Unger Road, between Firdale and Dixon Mill roads: complete
  • Withycombe Road, between Springhill Road and end-of-pavement: complete
     

Paving (updated 9/17/21)

  • 68th Place, between Ashdale Drive to the cul-de-sac (URMD): July 20, Aug. 3-4 - complete
  • 75th Avenue, between the barricades and Oak Street (URMD): July 8-9 - complete
  • 78th Avenue, between Fairway Drive and Canyon Drive (URMD): July 14-16, 21, 26 - complete
  • 81st Avenue, between Garden Home Road and dead-end (URMD): July 14, 19 - complete
  • 86th Avenue, between Cecilia Terrace and Bohmann Parkway (URMD): July 14 - complete
  • 89th Avenue, between Garden Home Road and the cul-de-sac (URMD): July 13, 19 - complete
  • 90th Avenue, between Garden Home Road and Rambler Lane (URMD): July 8-9, 12, 26 - complete
  • 94th Avenue, between Garden Home Road and Moss Street (URMD): July 9, 14 - complete
  • 95th Avenue, between 95th Avenue and the cul-de-sac (URMD): July 22, 30 - complete
  • 103rd Avenue, between Arborcrest Way and Melnore Street (URMD): July 15, 21, 26, 28 - complete
  • 134th Avenue, between Butner Road and Evergreen Street (URMD): July 23, 26, 28 - complete
  • 142nd Avenue, between Devenwood Avenue and Todd Street (URMD): July 23, 26 - complete
  • 195th Court, between Anderson Street to the cul-de-sac (URMD): July 29-30 - complete
  • 196th Avenue, between Anderson Street and house #4520 (URMD): July 28-29 - complete
  • 196th Avenue, between Pike and Cascadia streets (URMD): July 28-29 - complete
  • Bethany Boulevard, between West Union and Kaiser roads (Road Fund): Delayed until further notice
  • Bohmann Park, Between 87th Avenue and Becker Drive (URMD): July 13-15 - complete
  • Brier Lane, between 90th and 92nd avenues (URMD): July 12, 14 - complete
  • Charming Way, between Newton Place and the private drives (URMD): July 14-19, 21 - complete
  • Garden Lane, between 84th and 87th avenues (URMD): July 13, 19 - complete
  • Hemlock Street, between the private drives and the dead end (URMD): July 8-9 - complete
  • Joss Avenue, between Springville and Brugger roads (Road Fund): Aug. 16-20 - complete
  • Kinnaman Road, between 180th and 185th avenues (Road Fund): Delayed until further notice
  • Laurel Street, between 103rd and 107th avenues (URMD): July 16, 22, 28 - complete
  • Mapleleaf Street, between 85th Avenue to the dead-end (URMD): July 8-9 - complete
  • Moss Street, between 93rd Avenue and the private drive (URMD): July 9, 14 - complete
  • Muirwood Drive, between Woodward Way and Portola Avenue (URMD): July 22-23, Aug. 3-4 - complete
  • Newton Place, between Dogwood Lane and dead-end (URMD): July 14-19, 21 - complete
  • Oleson Road, between Oleson Road and the dead-end (URMD): July 15, 20-21 - complete
  • Perfecta Avenue, between Tropicana Avenue and the dead-end (URMD): July 27-29 - complete
  • Pheasant Drive, between Augusta Lane and the dead-end (URMD): July 28-29 - complete
  • Rambler Lane, between 87th and 92nd avenues (URMD): July 12, 14, 26, 29-30 - complete
  • Science Park Drive, between Murray Boulevard and Cornell Road (Road Fund): Sept. 15-17
  • Tropicana Avenue, between Butner Road and Perfecta Avenue (URMD): July 27-29 - complete

 

Pavement repair (updated 9/20/21)

  • 185th Avenue, between Farmington Road and Madeline Street: Aug. 18-19 - complete
  • Cornell Road, between Ray Circle and Butler Street: Sept. 16-20 (weekdays only) - complete
  • ock Creek Boulevard, between 185th Avenue and Cornelius Passs Road: Aug. 20-24 - complete
  • Roshak Road, between Snapdragon Lane and Barrows Road: Aug. 16 - complete
  • Terman Road, between Murray Boulevard and Hocken Avenue: Aug. 17 - complete
  • Tualatin-Sherwood Road, between 97th Avenue and Nyberg Street: Aug. 25-27 (8 p.m.-5 a.m.) - complete