Scholls Ferry and Scholls-Sherwood Roads Intersection
Current Activity - completed
Activity Update 2/27/2020: The new traffic signal at the Scholls Ferry and Scholls-Sherwood roads intersection. Please slow down and be prepared to stop. Additional lane closures will be required for final paving.
Past updates:
___________________________________
Activity Update 1/24/2020: Signal poles have been installed, but are not yet activated. Construction is expected to continue through February.
Activity Update 10/15/2019: Construction is underway with completion anticipated by Jan. 31, 2020.
Activity Update 10/3/18: Open house exhibits are now available in the Design section of this page.
Activity Update 9/19/18: An open house will be held 5-7 p.m. Wednesday, Oct. 3 at Groner K-8 School, 23405 SW Scholls Ferry Road.