Augusta Lane (FY 2016-17 URMD Safety Improvement)

Project Timeline

Estimated completion date: 09/30/2021

 

  • Survey and studies: Winter 2019-Winter 2020
  • Preliminary designs: Spring 2019-Spring 2020
  • Permitting: Winter-Summer 2020
  • Open house: April 6-26, 2020
  • Final design: Spring-Summer 2020
  • Contractor bid process: November 2020
  • Construction kickoff: Jan. 22-31, 2021
  • Start of construction: Jan. 25, 2021
  • Project completion (tentative): September 2021

Note: Dates are estimates and subject to change.