Walker Road/Murray Boulevard Intersection

Current Activity - design

 

Activity Update 10/17/2019: This project is tentatively expected to begin construction is October 2020.

 

 

Past Updates
_______________________ 

Activity Update 1/10/2019: Project design is nearly 90% complete. Right-of-way acquisition is underway. Permitting is scheduled start in March. Project is expected to go out for bid in spring 2020 with construction dates dependent on Jenkins Road project dates.

 

Activity Update 6/5/2018: Open house exhibits are now available in the Design section of this page.

 

Activity Update 2/27/2018: Project schedule is now late spring 2019 thru fall 2020. Right-of-way acquisition has begun and is expected to be complete by end of 2018.

 

Activity Update 11/7/2017: Project has been expanded to include improvements to the Walker Road and Park Way intersection. A traffic signal will be installed. Project construction is estimated to begin in Spring 2019.

 

 

Activity Update 4/20/2016: An open house will be held on Monday, May 16 from 5 to 7 p.m. at Holy Trinity Parish. The public is invited to stop by to learn more about planned improvements for the intersection and to provide comments to the project team. No formal presentation is planned.

May 16 Open House Postcard
 


Project e-Newsletters

May 2016