Walker Road Phase 2 (Schendel to Murray)

Current Activity - design


Activity Update 6/4/2018: Exhibits from the May 30 open house are now available on the Design section of this page.


 

Past Updates
_______________________ 

 

Activity Update 2/26/2018: Project schedule is now late spring 2019 thru fall 2020. Right-of-way acquisition will begin in late spring 2018 and is expected to be complete by end of 2018.


Activity Update 5/26/15: Phase 2 of the Walker Road project is scheduled to begin construction in 2018.

In the meantime, Phase 1 of the Walker Road project (173rd to Schendel) and 158th Avenue (Walker to Merlo Station) are moving forward and anticipated to begin construction spring 2016 with completion by November 2016.

The following is a map showing the tentative schedule for all projects in the area, including phase 1 of the Walker Road project (173rd to Schendel). Dates and project limits are subject to change.

Walker area projects vicinity map (as of May 2015)