Walker Road - Phase 3

Walker Road Phase 3 logoProject Description

This project will widen SW Walker Road, between 173rd and 185th avenues, to five lanes, two travel lanes in each direction and a center turn lane. The project includes replacement of culvert at Willow Creek, a traffic signal at 178th Avenue/Cambray Street, continuous bicycle and pedestrian facilities, storm drainage upgrades, street lighting, sound walls and landscaping.

This is the third phase of improvements to Walker Road. 

 

Funding Information

The $8 million project is funded through the County's Major Streets Transportation Improvement Program (MSTIP).

 

Community Participation Program CPO 7
Commissioner District 2

 

Media Releases

Open house for Walker Road is Aug. 8

 