195th Avenue (FY 2022-24 Pedestrian & Biking Improvement)

The sidewalks on 195th Avenue from Keena Court to Farmington Road don’t all connect.

We will build sidewalks along the west side of the road that will connect to Farmington Road. This project is part of a larger effort to connect sidewalks and walkways in the Aloha area. We will build this at the same time as the 188th Avenue sidewalk project.

Construction start (expected): Summer 2024
Construction finish (expected): Fall 2024

Update

4/22/2024: The right-of-way acquisition process is underway.

Funding

Cost: $359,000 (2022 estimate)

Funding sources:

Urban Road Maintenance District (URMD)

Prior events and comment opportunities

Online open house: Oct. 21- Nov. 6, 2022